Sr No |
Name of the Project | Location of the Project | Client | Project Cost (In Lacs) |
---|---|---|---|---|
1 | Earthen Embankment Raw Water Reservoir of 2.5 Million Cubic Meters Capacity near 2x600 MW Singareni Thermal Power Project site | Andhra Pradesh | The Singareni Collieries Company Limited, Power Project Division | 2500.00 |
2 | Earthen Dam near Shahapur, Mumbai | Maharashtra | Parasrampuria Plantations Ltd | 220.00 |
3 | FRL Demarcation Survey for Padalase Dam (Lower Tapi Project) of Tapi Irrigation Development Corporation | Maharashtra | Srinivasa Constructions Ltd | 113.00 |
4 | FRL Demarcation Survey for Shelgaon Barrage of Tapi Irrigation Development Corporation | Maharashtra | Pioneer Constructions | 40.00 |